UK & Ireland Featured Project: FT Pipeline Systems - Integrated Management System (1254)

QEM Solutions used their understanding of the water industry to develop a management system that satisfied the requirements of ISO 9001:2008, ISO 14001:2004 and OHSAS 18001:2007. QEM Solutions continue to manage and improve the organisations processes both on a corporate and project specific level.

Tell Me More...
Overseas Featured Project: Capita Symonds - Valve Inspections

QEM Solutions were contracted to carry 3rd party inspection and witnessing activities on a series of valves fabricated in Germany for a series of SGN contracts throughout Scotland.

Tell Me More...
We are QEM Solutions We are QEM Solutions

We are problem solvers. We are organisers. From the project start-up to the very final evaluations and analysis, we can bring enthusiasm to each and every part of your project.

 

 
Our projects

Our Projects

Combined, we have over 50 years experience, gained on a variety of projects throughout the world. But no two engineering projects are alike.

Sometimes we manage a project from the very start and continue to be involved until the end reports. Other times we are brought in to provide specialist services in specific areas. Each brings different challenges. Each has different outcomes.

We would like to share just a few of these projects here.

Show map

Our Projects

AMEC - Easington to Paull, Paull to Goxhill & Goxhill to Hatton Pipelines and AGI’s Technical Writing

AMEC Industrial

North East England
1 Mar 2007 - 1 Dec 2007

AMEC Industrial were awarded a contract to produce the design for the construction of 3 pipelines and associated AGI's. The pipelines were to span from Easington to Paull, Paull to Goxhill and Goxhill to Hatton.

Each one requiring segregated design processes and deliverables.

QEM Solutions were contracted to Assist the Amec / National Grid Alliance with the development of existing and new design processes in line with CDM and National Grid requirements.

Benefits of engaging QEM Solutions:

  • Part-time assistance as and when necessary.
  • Development of industry best practice. 
  • Commitment to "Get The Job Done".

Responsibilities included:  

  • Identification of project deliverables in accordance with work information. 
  • Working with the existing Tech SHE team to establish new processes. 
  • Creation of project Design Plans & associated design processes. 
  • Gap Analysis on internal Amec processes in line with contract requirements. 
  • Creation of Project Quality Management processes & Plan. 
  • Development of best practice risk mitigation during the design process.

 Services Breakdown

  Design Co-ordination
  Quality Management

 Engaged Specialists