Spiecapag - PNG LNG Pipeline (586)
Engineering & Site Management
Spiecapag, PNG LNG
Brisbane, Australia & Papau New Guinea
1 Feb 2010
-
1 Dec 2010
Spiecapag were awarded the onshore section of the larger PNG LNG project which connects the offshore pipeline and the LNG facility site, a distance of approximately 300km. QEM Solutions were able to provide the Main Works Contractor with resources to assist the QA/QC & Engineering teams.
Benefits of Engaging QEM Solutions included:
-
Hiting the ground running with the correct knowledge and experience with no further delay to the project.
-
Providing key skills that wererequired for the prosition.
-
Providing a clear and concise liaison & communication between the multi lingual colleagues and client / contractor.
Primary responsibilities included:
-
Writing Technical reports, Schedules and Calculations, Method Statements, Inspection & Test Plans and Management Procedures.
-
Assisted construction teams on visits to Papa New Guinea to manage initial surveying & clearance crews.